Guta2 meter high electric elevatorDesign features explored

announcer:hp935HP175192871 release time:2023-12-24 10:17:41

Setting requirements: When the distance between the outer edge of the construction electric elevator and the external overhead power line cannot meet the requirements of a small safety distance, with a size of 8 meters by 2 meters.

Guta.Installation position of upper limit switch: Under normal working conditions, the distance between the upper limit switch and the upper limit switch is 0.15m for SC type construction electric elevators, intermediate shafts and bearings,Guta10 meter electric elevator, oil cylinder pin shafts and bearings, boom hinge shafts and bearings for wear. Add some oil to each part to extend the service life of the lifting platform bearings. The quality and level of hydraulic oil. The lifting platform should be raised throughout the entire process, and at this position, the hydraulic ground should be 40-50 millimeters higher than the bottom of the box. If the hydraulic oil becomes dark, sticky, or has foreign objects such as gravel, it should be replaced in a timely manner (32 # hydraulic oil). Annual maintenance and inspection of all hydraulic pipelines and joints of the lifting platform. The pipeline must not be damaged, and the joints must not be loose. All joints must be tightened. Remove and disassemble the lowering valve of the lifting platform, blow out the plunger with compressed air then install it and reinstall it. Drain and discard the hydraulic oil, tighten the joint remove the oil filter, clean it with compressed air and then return it to the oil tank and connect the pipeline.

.The landing door should be in a normally closed state. Without the permission of the construction electric elevator driver, the landing door shall not be opened.

When a rigid 5000mm2 square or circular flat surface is applied with a normal force of 600N to either side of the door, the door may not meet the above requirements, but safety should be maintained.

Before operating the construction electric elevator, routine inspections should be carried out according to regulations and inspection records should be filled out.


Guta2 meter high electric elevatorDesign features explored



The advantages and disadvantages of several commonly used electric lifting mechanisms are as follows: hydraulic electric lifting mechanisms: using hydraulic technology, smooth lifting and low noise.

Afterwards, it should be scrapped.

Later, when there is a major malfunction of the lifting platform, it should be repaired by professional personnel as soon as possible. After the malfunction occurs, it should not be used again to avoid accidents, personnel and property losses.

Economic management.The safety bulletin board for construction electric elevators should be hung at the protective shed of the electric elevator, with a size of 8 meters by 2 meters.

Setting requirements: For construction electric elevators with foundations installed on roof slabs, floors, or other lower suspended structures, the bearing capacity of the foundation support structure should be checked. Click here to download the construction technical information for free. Basic drainage facilities should be installed.

High lifting height, using side mounted oil cylinders, stable operation, easy maintenance, and longer service life.


Guta2 meter high electric elevatorDesign features explored



Once again,GutaElectric lifting platform 2 meters, weekly inspections should be conducted to check whether the connecting screws at various parts of the lifting platform are tightened, whether the sealing rings are damaged or ineffective, whether there is a lack of hydraulic oil, and whether the oil cylinder is leaking. It is necessary to clean the lifting frame, scissors, wiring, and oil cylinder once a week to avoid dust and debris affecting normal operation.

Total quality management.Setting requirements: The spacing of wall brackets along the vertical direction should comply with the provisions of the user manual.

The cargo is 0.5m.

Steel wire ropes,GutaLight electric elevator, pulleys, and counterweight steel wire ropes shall comply with the following regulations: the characteristics of steel wire ropes shall comply with the requirements of General Purpose Steel Wire Ropes GB/T20118; Maintenance, wear, deformation, and corrosion of steel wire ropes

Guta.The bearing capacity of the ground under the concrete foundation plate should be greater than 0.15Mpa.

The bearing capacity of the building structure at the attachment point of the wall bracket should meet the requirements specified in the user manual for construction electric elevators.

The angle between the wall bracket and the horizontal plane should comply with the requirements of the user manual.